The architect company A-lab solved a complex construction with BIM

A-lab

Advanced BIM modeling made it possible to construct a 65.000/117.000 m2 commercial building complex, the Statoil building at Fornebu, Norway, in only 20 months on site.

Thanks to thorough planning, advanced BIM-modeling and a fruitful solution-oriented dialogue, the team behind the realisation of this project - the client and owner, construction companies, all subcontractors and last but not least the architects from A-Lab along with their trusted BIM advisors from Symetri, were able to complete the complex design of the Statoil construction on schedule. Initially, when the A-Lab team started designing and planning the Statoil building, it was still in the early days of BIM management. However, the BIM manager and architect at A-Lab, Angie Arroyo Mendez, saw no other way than to start working with BIM using IFC.

 

 

Challenges

  • Implementation of BIM / IFC – upgrading from ACAD
  • Development of methodology

Solutions

  • Customised solution with Naviate add-on to Revit
  • Coaching and teaching of new methodology
  • Solibri – visualising 

Benefits

  • Challenging questions are answered with high end solutions
  • Through discussions with skilled people, we learn something new all the time
  • Consultancy made the further development possible = time saving procedures
  • Skanska saved 10% of the costs on site by fixing the problems virtually in Solibri
  • A support team on a Scandinavian level yet close to Autodesk makes a difference

For more information, please contact

Per Carlsson
Per Carlsson
Director, Building & Infrastructure
Per Ole Otterness
Per Ole Otterness
Building & Infrastructure
Jyrki Petsalo
Jyrki Petsalo
Building & Infrastructure
Henrik Munk Madsen
Henrik Munk Madsen
Building & Infrastructure

Leave us a message


Ripellino ensures growth with BIM

When the architectural firm Alessandro Ripellino decided to take the step to BIM planning, in order to meet changing purchaser requirements, it was important to have a user-friendly platform and to be able to deliver high-quality projects in a short time.

The time of paper copies out in the field has passed

Thanks to BIM 360 Field, the whole building site is being digitised and not just the drawing and the model. All the work that so far has been done around the computer screen in the ‘building shed’ is now being moved out to the building site.